West Davis

This is an Alert Bar!

What's Happening Now

(Please note that each update item is now color coded to correspond to a general area along the corridor alignment. Teal covers Centerville and Farmington. Light blue covers Kaysville and Layton. Dark blue covers Syracuse and West Point.)

East Frontage Road (Farmington) (NEW)

  • The East Frontage Road is fully closed between 1340 South and Jennings Lane until Friday, December 24th, when the road will be paved and reopened to traffic. This closure is necessary to provide needed work space and to keep the work on schedule.
  • Prior to construction, the project team decided to permanently shift the East Frontage Road to the east to avoid any significant impacts to I-15. This shift is needed to build the northbound I-15 offramp to the northbound West Davis Corridor. Crews will still be working on drainage infrastructure, boring under I-15, and utility relocations as this shift occurs.

I-15 (Farmington) (NEW)

  • As early as Monday, December 6th, crews will conduct test pile driving operations along northbound I-15 for the future northbound West Davis bridge.
  • Steel sheet pile driving will then begin as early as Friday, December 17th. These steel sheets will serve as future retaining walls for this portion of the corridor.
  • There will be a double left lane closure on northbound I-15 from 8 p.m. on Thursday, December 9th to 6 a.m. on Friday, December 10th for geotechnical surveys.

Denver and Rio Grande Trail (Farmington) (NEW)

  • Paving work is expected to begin on the Denver and Rio Grande Trail below Glovers Lane in Farmington on Wednesday, December 8th.
  • To accommodate this work, pedestrian traffic along the trail will be detoured to 800 West for approximately one week.
  • Pile driving activities at the Denver and Rio Grande Trail will begin as early as Wednesday, December 15th.

Bluff Road (Syracuse)

  • Installation of a new water line is underway on Bluff Road, progressing southward from 3000 West.
  • The Bluff Road southbound lane closure will be in effect until 2022.  Drivers will still be able to travel northbound on Bluff Road but will be detoured to 3000 West when traveling southbound.

700 South (Syracuse)

  • Drainage and sewer line installations are expected to wrap up along 700 South between 3000 West and 4000 West by Monday, December 6th. This segment will then reopen to through traffic and all sidewalks will reopen to pedestrians.

Looking Ahead

  • In mid-December, Central Davis Sewer District will be installing a new sewer line along 650 West in Farmington. Traffic impacts will be announced as the start date approaches for this work.
  • Several current and upcoming Syracuse City projects will coincide with West Davis construction.
    • North Davis Sewer District is conducting work at 3000 West and 2900 South through mid-December. This area will be closed to all traffic through completion.
    • Paving work at 1200 South and 4500 West in West Point is anticipated to occur within the next several weeks.
    • Manhole installment/replacement work for the Black Island Farms development at 4000 West and 2200 South is anticipated to finish in Spring 2022.
  • Sewer line installation is expected to begin on Antelope Drive by Monday, December 13th. This work will continue through early January. There will be no work project-wide after Christmas Eve (Friday, December 24th) until Monday, January 3rd.

Ongoing Project Work

UDOT will continue with design work, utility coordination, debris clearing, fence installation, and drainage installation. The West Davis project team will also continue to coordinate closely with residents, businesses, city leadership, and other key stakeholders.

Schedule is subject to change due to equipment, material, utility and/or weather delays.

Project Overview

West Davis is a new 16-mile, 4-lane divided highway that will be constructed in western Davis County between the I-15/Legacy Parkway junction at approximately Glovers Lane in Farmington and the future extension of S.R. 193 in West Point. A map of the project alignment is available here.

Freeway-style interchanges with on- and off-ramps will be built at Legacy/I-15
(Farmington), 950 North (Farmington), 200 North (Kaysville), 2700 West (Layton), 2000West (Syracuse), and Antelope Drive (Syracuse).

West Davis will include over 10 miles of new trail and new trail connections to create a consolidated system connecting Emigration Trail to Legacy Parkway Trail.

Stay Informed

Questions? Comments? Contact the Public Involvement Team at 877-298-1991 or westdavis@utah.gov.

Follow West Davis on Facebook!

The West Davis Highway Facebook group is now live! Residents can now conveniently stay up to date on critical project information, impacts, activities, schedule, etc. and post questions for the project team. Click here to join!

Project Notices

Click below to learn about the Antelope Drive Frontage Roads State Environmental Study .

Click below to learn about the Layton Canal relocation construction project now underway .

Schedule

Pre-Construction Design
2019 – Winter 2020

Construction
Spring 2021 – Winter 2024

Project Notices

Project update lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet dolore magna aliquam erat

Project update lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet dolore magna aliquam erat

Project update lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet dolore magna aliquam erat

Contact Us

Hotline
877-298-1991

Contact Us

877-298-1991

Hotline
877-298-1991

Email
Send a Message

Facebook
Group

Comment Form
Submit Comment