West Davis

This is an Alert Bar!

What's Happening Now

(Please note that each update item is now color coded to correspond to a general area along the corridor alignment. Teal covers Centerville and Farmington. Light blue covers Kaysville and Layton. Dark blue covers Syracuse and West Point.)

I-15 (Farmington) (NEW)

  • Beginning Monday, November 28, through the end of January, crews will conduct intermittent night work on I-15 in Farmington. The work will need to be conducted at night to reduce travel impacts on I-15. Trucks will be hauling excavated material from I-15 at night along the new corridor and public roads to the new corridor between 1525 West and 950 North. Please expect increased amounts of light and noise during this time. This schedule is subject to change due to equipment, material, utility and/or weather delays.
  • The outside southbound I-15 shoulder continues to be closed through the end of 2023, approximately one mile south of Glovers Lane.
    • This closure will allow crews to continue working safely to build the new bridges connecting West Davis Highway to I-15.

Legacy Parkway (Farmington) (NEW)

  • On Friday, November 18, the northbound right lane on Legacy Parkway near milepost ten will be closed from 5 a.m. to 12 p.m. for concrete pouring.

Schick Lane (200 North) (Kaysville) (NEW)

  • Nightwork on Schick Lane will begin Tuesday, November 15, through Thursday, November 17, between the hours of 7 p.m. to 6 a.m. Schick Lane between 2950 West and Island Way will be closed to allow crews to place girders for the future overpass.

South Bluff Road (Syracuse)

  • One-way flagging operations will continue through Wednesday, November 23 on Bluff Road between Antelope Drive and 2700 South to facilitate Storm Drain installation.

2000 West (Syracuse)

  • One-way flagging operations will continue  through Wednesday, November 23 on 2000 West between 3000 South and Combe Road to facilitate Storm Drain and waterline installation.

Gentille Street (Syracuse) (UPDATE)

  • Nightwork on Gentile Street has been pushed back. Work will begin sometime after the Thanksgiving holiday weekend.

Antelope Drive (Syracuse)

  • Through mid-November, traffic between 3000 West and 3300 West will be shifted to the North side of Antelope Drive to facilitate work on the south side of Antelope Drive.

Ongoing Project Work

UDOT will continue utility coordination, debris clearing, fence installation, drainage installation, bridge construction, and paving for this major new highway. The West Davis project team will also continue to coordinate closely with residents, businesses, city leadership, and other key stakeholders. 

Schedule is subject to change due to equipment, material, utility and/or weather delays.

Project Overview

West Davis is a new 16-mile, 4-lane divided highway that will be constructed in western Davis County between the I-15/Legacy Parkway junction at approximately Glovers Lane in Farmington and the future extension of S.R. 193 in West Point. A map of the future highway is available on the project website here.

Freeway-style interchanges with on- and off-ramps will be built at Legacy/I-15 (Farmington), 950 North (Farmington), 200 North (Kaysville), 2700 West (Layton), 2000 West (Syracuse), and Antelope Drive (Syracuse). 

West Davis will include over 10 miles of new trail and new trail connections to create a consolidated system connecting Emigration Trail to Legacy Parkway Trail.

Stay Informed

For more information, visit westdavis.udot.utah.gov. Questions? Comments? Contact the Public Involvement Team at 877-298-1991 or westdavis@utah.gov.

Follow West Davis on Facebook!

The West Davis Highway Facebook group is now live! Residents can now conveniently stay up to date on critical project information, impacts, activities, schedule, etc. and post questions for the project team. Click here to join!

Project Notices

Click below to learn about the Antelope Drive Frontage Roads State Environmental Study .

Click below to learn about the Layton Canal relocation construction project now underway .

Schedule

Pre-Construction Design
2019 – Winter 2020

Construction
Spring 2021 – Summer 2024

Project Notices

Project update lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet dolore magna aliquam erat

Project update lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet dolore magna aliquam erat

Project update lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet dolore magna aliquam erat

Contact Us

Hotline
877-298-1991

Contact Us

877-298-1991

Hotline
877-298-1991

Email
Send a Message

Facebook
Group

Comment Form
Submit Comment