West Davis

What's Happening Now

Utility Potholing
As early as Monday, April 5 and continuing through May, crews will begin potholing and performing video inspection of existing pipes at various locations throughout the project area to identity underground utilities.  Work will take place during daytime hours Monday – Friday.

Along the I-15 East Frontage Road in Centerville and Farmington City, potholing will be conducted in the shoulder of the roadway. Flaggers will be stationed near workers and equipment to assist with the flow of traffic and to maintain safety. Access will be maintained during this activity.

Along Antelope Drive (1700 South) in Syracuse, existing storm drain and irrigation pipe lines will be cleaned and video inspected from 9 p.m. to 6 a.m. Monday – Friday.  This work will require shoulder closures along Antelope Drive. Please obey all traffic control signs and flagger signals while traveling through these areas.

Additional potholing and pipe inspection work will continue after the East Frontage Road work is complete during daytime hours Monday – Friday in various areas along the project corridor.  These areas include:

1.    Farmington – Glovers Lane, Shirley Rae, 800 West and 650 West
2.    Kaysville – Angel Street and 200 North
3.   Layton – Weaver Street and 3200 West
4.   Syracuse – 1000 West and Gentile Street

Potholing and pipe inspection work will continue during night time hours along I-15 and Legacy Highway between Parrish Lane and the Glovers Lane overpass off the pavement in the shoulders.  No traffic impacts are anticipated.  This work should begin after the Antelope Drive potholing work is complete.

Legacy Pile Driving
Pile driving in the Legacy Highway median at approximately mile marker 10 is expected to continue intermittently for an additional three weeks. The median will be closed to accommodate this activity until pile driving has concluded.

Follow West Davis on Facebook!
The West Davis Highway Facebook group is now live! Residents can now conveniently stay up to date on critical project information, impacts, activities, schedule, etc. and post questions for the project team. Click here to join! 

Looking Ahead

Hauling Fill Material Begins April 19
As early as April 19, crews will begin hauling fill (dirt) material out to the project site, beginning in Farmington. Residents should expect heavy and persistent truck traffic along main local roads for several months as the hauling moves south to north. 

UDOT will continue with design work, utility coordination, debris clearing, and property acquisition and preparation. The West Davis project team will also continue to coordinate closely with residents, businesses, city leadership, and other key stakeholders.

Project Notices

Click below to learn about the Antelope Drive Frontage Roads State Environmental Study .

Click below to learn about the Layton Canal relocation construction project now underway .

Schedule

Pre-Construction Design
2019 – Winter 2020

Construction
Spring 2021 – Winter 2024

Project Notices

Project update lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet dolore magna aliquam erat

Project update lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet dolore magna aliquam erat

Project update lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet dolore magna aliquam erat

Contact Us

Hotline
877-298-1991

Contact Us

877-298-1991

Hotline
877-298-1991

Email
Send a Message

Facebook
Group

Comment Form
Submit Comment