West Davis

This is an Alert Bar!

What's Happening Now

(Please note that each update item is now color coded to correspond to a general area along the corridor alignment. Light blue covers Centerville and Farmington. Dark blue covers Kaysville and Layton. Orange covers Syracuse and West Point.)

East Frontage Road

  • Crews will continue to install drainage, water, and irrigation pipes along the East Frontage Road between 1600 South and 1700 South in Farmington until mid-October.
  • Power conduit and feeder box relocations will begin next week and continue until the end of October.
  • There will be one-way flagging operations on 1470 South between 7 AM and 5 PM for the duration of next week.
  • There will be temporary removal of some noise walls along the East Frontage Road in Centerville and Farmington in early October. This work is unrelated to the approved noise walls for the West Davis highway, including an additional noise wall in Centerville.
  • Pedestrian access will remain closed in this area.

1350 South

  • Crews will begin clearing debris to place a gas line along approximately 1350 South in Farmington as early as Monday, October 4th.
  • Drainage pipe installation will subsequently occur over the course of the following week.

Glovers Lane

  • As early as Tuesday, October 5th, crews will begin installing drainage pipes along Glovers Lane around 1100 West.
  • There will be lane shifts during daytime hours to accommodate for this work, but no closures are expected.
  • This work is anticipated to conclude in approximately one week.

Legacy Parkway

  • Nightly lane closures on northbound and southbound Legacy Parkway at mile post 10 will occur until mid-October.
  • Crews will be installing temporary pavement and new conduit during this time.

Antelope Drive

  • The weekend of October 2nd (Friday to Sunday evening), there will be a full closure of Antelope Drive between the east side of 3000 West to the west side of Bluff Road for demolition of the pedestrian underpass.
  • This work is anticipated to last from Friday at 9 PM until completion, but no later than Monday at 6 AM. This one-time weekend closure avoids multiple daily closures over a longer period of time and minimizes impacts to residences and businesses.
  • Please follow all posted detours and signage during this work. The public will be detoured off of Antelope onto Bluff Road and 3000 West.

Noise Walls

  • UDOT has approved five noise walls for construction.
  • There will be two walls in Centerville along the East Frontage Road, one wall along the Syracuse Stillwater development, one wall along the Fremont Crest development, and one wall running parallel to Steed Drive in Syracuse. More information can be found on our noise wall page. 
  • Installation of noise walls is anticipated to begin in the spring of 2022.

Looking Ahead

  • Utility relocations are expected to begin along Bluff Road between Antelope Drive and 3000 West in early mid-October.
  • To facilitate this work and other reconstruction through the area, Bluff Road traffic will be restricted to one-way northbound. Southbound traffic will be detoured to 3000 West beginning October 4th through fall 2022.
  • In mid-October, crews will begin excavating large bore pits along northbound I-15 in Centerville and Farmington. This work will continue for approximately four months.

Ongoing Project Work

UDOT will continue with design work, utility coordination, debris clearing, fence installation, and drainage installation. The West Davis project team will also continue to coordinate closely with residents, businesses, city leadership, and other key stakeholders.

Schedule is subject to change due to equipment, material, utility and/or weather delays.

Project Overview

West Davis is a new 16-mile, 4-lane divided highway that will be constructed in western Davis County between the I-15/Legacy Parkway junction at approximately Glovers Lane in Farmington and the future extension of S.R. 193 in West Point. A map of the project alignment is available here.

Freeway-style interchanges with on- and off-ramps will be built at Legacy/I-15
(Farmington), 950 North (Farmington), 200 North (Kaysville), 2700 West (Layton), 2000West (Syracuse), and Antelope Drive (Syracuse).

West Davis will include over 10 miles of new trail and new trail connections to create a consolidated system connecting Emigration Trail to Legacy Parkway Trail.

Stay Informed

Questions? Comments? Contact the Public Involvement Team at 877-298-1991 or westdavis@utah.gov.

Follow West Davis on Facebook!

The West Davis Highway Facebook group is now live! Residents can now conveniently stay up to date on critical project information, impacts, activities, schedule, etc. and post questions for the project team. Click here to join!

Project Notices

Click below to learn about the Antelope Drive Frontage Roads State Environmental Study .

Click below to learn about the Layton Canal relocation construction project now underway .

Schedule

Pre-Construction Design
2019 – Winter 2020

Construction
Spring 2021 – Winter 2024

Project Notices

Project update lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet dolore magna aliquam erat

Project update lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet dolore magna aliquam erat

Project update lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet dolore magna aliquam erat

Contact Us

Hotline
877-298-1991

Contact Us

877-298-1991

Hotline
877-298-1991

Email
Send a Message

Facebook
Group

Comment Form
Submit Comment