SR-177 (West Davis)
Welcome to SR-177 (West Davis)
SR-177 (also known as West Davis Highway) is a 16-mile highway that currently stretches from Farmington to West Point, with more than 10 miles of trails. UDOT is currently working on a project to extend the highway 2.5 miles north to 1800 North in West Point and extend the Emigrant Trail from 1300 North to the Weber County line. This project will provide Utahns more choices in the way they travel.
What's Happening
Construction activities beginning this July!
SR-177 (West Davis Highway) extension is moving from design into construction!
As early as this week, crews will begin preliminary construction activities along the project corridor from 700 South to 1800 North. Initial work will include vegetation and brush clearing, construction fencing, environmental mitigation activities, and other site preparation needed before major construction begins.
This preliminary work is expected to continue through the end of July, generally starting on the south end of the project and moving north. Full construction activities are anticipated to begin during the first week of August.
One of the first major construction activities scheduled for August is pile driving near 700 South, marking the beginning of bridge construction work. Residents may notice increased construction activity, equipment, and crews in the area as work ramps up over the coming weeks.
Construction is generally scheduled Monday through Friday from 6 a.m. to 7 p.m. Weekend work may occur as needed. If nighttime work becomes necessary, nearby residents will be notified in advance.
Schedule